General Motors might be globalising its business, but in the area of servers, the auto-maker is thinking small. "The smallest physical-sized servers have a far better cost per unit of work than the large, 32-CPU-class boxes," says Mark Hillman, GM's director of global computing centres. The former will serve as building blocks as the company moves from a project-specific, application-centric focus to a standardised server utility model.

The effort started with engineering, but "now we're moving that to the more general-purpose business applications," says Hillman. The results so far have been promising. By shifting from vertically scaled servers to commodity systems, GM reduced operating costs by 65 per cent in its Toronto data centre. That project will continue through 2008, Hillman says.

GM isn't alone in planning major server projects for the year ahead. In sister publication Computerworld's most recent Vital Signs survey, servers topped the list of planned purchases for 2008, and nearly one in three respondents (32 per cent) said that server spending represents the single biggest increase in their IT budgets.

IT executives cite a litany of reasons for moving server-related projects to the front burner. Consolidation is a big one. Some organisations are also preparing for new versions of key software, such as Windows Server 2008, and servers that will come preloaded with an embedded VMware hypervisor to speed the setup of virtual machines. "That's one of the biggest things we'll see," says James Staten, an analyst at Forrester Research.

Then there are regular server refreshes. After the dot-com crash, many organisations began keeping equipment for four, five or even seven years rather than the usual three. Many of those systems are now being retired.

"Data centres today have a fairly old infrastructure. We find some very old boxes out there," says Klaus Schmelzeisen, vice president of HP's consulting and integration infrastructure practice.

Compared with the Pentium 4-class and older machines still in many data centres, the latest technology performs better, takes up less space and is far more energy efficient. New servers also use multi-core processors, which are better suited for the consolidation of the many Linux and Windows applications that continue to migrate onto virtual machines.

"Forty percent of our servers are virtualised," and that consolidation will continue in 2008, says Jim Hull, group head of network and operations services for MasterCard Worldwide's global technology and operations group.

The Bank of New York Mellon also plans to "hit the virtualisation space more" this year, says Dennis Smith, first vice president in the bank's IT group. Having just completed a merger last July, the bank is moving rapidly to establish hardware and software standards as it consolidates data centres. "We are speeding up the refresh cycle because of the need to do something quickly," Smith says.


Share:

More from Techworld

More relevant IT news

Comments



Send to a friend

Email this article to a friend or colleague:

PLEASE NOTE: Your name is used only to let the recipient know who sent the story, and in case of transmission error. Both your name and the recipient's name and address will not be used for any other purpose.

Techworld White Papers

Choose – and Choose Wisely – the Right MSP for Your SMB

End users need a technology partner that provides transparency, enables productivity, delivers...

Download Whitepaper

10 Effective Habits of Indispensable IT Departments

It’s no secret that responsibilities are growing while budgets continue to shrink. Download this...

Download Whitepaper

Gartner Magic Quadrant for Enterprise Information Archiving

Enterprise information archiving is contributing to organisational needs for e-discovery and...

Download Whitepaper

Advancing the state of virtualised backups

Dell Software’s vRanger is a veteran of the virtualisation specific backup market. It was the...

Download Whitepaper

Techworld UK - Technology - Business

Innovation, productivity, agility and profit

Watch this on demand webinar which explores IT innovation, managed print services and business agility.

Techworld Mobile Site

Access Techworld's content on the move

Get the latest news, product reviews and downloads on your mobile device with Techworld's mobile site.

Find out more...

From Wow to How : Making mobile and cloud work for you

On demand Biztech Briefing - Learn how to effectively deliver mobile work styles and cloud services together.

Watch now...

Site Map

* *